Timeline/Next Steps
Current Timeline
- 2006 - Complete planning and coordination of roads, interchange, and utility routes for the first phase of Discovery Ridge. Move and raze buildings as necessary to prepare site for the possibility of construction on parts of Discovery Ridge to occur as early as July 1.
- 2007 - Construction of interchange, service roads, and utility routes to serve Discovery Ridge.
- 2008 - Completion of the interchange and service roads for all of phase I of Discovery Ridge with the exception of Gans Road east, which has yet to have a timetable set for completion.