EXPRESS SCRIPTS HALL ELEVATOR UPGRADE
Advertisement Bids
Sealed bids for: EXPRESS SCRIPTS HALL ELEVATOR UPGRADE
Project Number: S7764
Status: Inactive
Advertisement Date: 07/11-2019
Campus: St. Louis
Construction Estimate: $531,000
ADVERTISEMENT FOR BIDS
Sealed Bids for:
EXPRESS SCRIPTS HALL ELEVATOR UPGRADE
and/or
WOODS HALL ELEVATOR UPGRADE
UNIVERSITY OF MISSOURI – ST. LOUIS
PROJECT NUMBER S7764
will be received by the Curators of the University of Missouri, Owner, at UMSL Campus Facilities Management, MSC North Garage, Reception, University of Missouri – St. Louis, 63121, until Thursday, December 5, 2019, 1:00pm, and then immediately opened and publicly read aloud in the MSC Garage, Room S-08.
Please note that bids are requested for each building elevator upgrade separately (Express Scripts Hall and Woods Hall) as well as a combined bid for elevator upgrades at both buildings.
Drawings, Specifications, and other related contract information may be obtained at http://www.x-rhodesplanroom.com. Electronic bid sets are available at no cost and may be printed as desired by the plan holders. No paper copies will be issued. If paper copies are desired, it is the responsibility of the user to print the files or have them printed. Bid results will be available the day after the bid opening by 3:00pm on the Cross Rhodes website (www.x-rhodesplanroom.com).
Questions regarding the scope of work and commercial conditions should be directed to
Gary Dedeke at email gdedeke@archimages-stl.com. All questions must be submitted in writing, via email or postal mail at 143 West Clinton Place, St. Louis, MO 63122.
A pre-bid meeting will be held on Tuesday, November 19, 2019 at 10:00am, at UMSL Campus Facilities Management, MSC North Garage, Conference Room S-08, University of Missouri – St. Louis, St. Louis, MO 63121, followed by a walk through at the sites.
A Supplier Diversity Participation goal: The projects shall have a separate 3% SDVE participation goal and a 3 point preference will be granted to SDVE bidders on all projects. All other bidders will be granted the 3 point bonus, if they achieve the 3% SDVE participation goal. For the participation goal, subcontractor and suppliers may be counted towards the goal. The project goal will be a 20% combined supplier diversity goal for MBE, WBE, Veterans, and BBE and a 3% goal for SDVE.
The Owner reserves the right to waive informalities in bids and to reject any and all bids.
Individuals with special needs as addressed by the Americans with Disabilities Act may contact Betty Covington (314) 516-5206.
Bound Spec - Express Scripts Hall
Reviewed 2020-11-04